Solar Installation Timeline in Madison, WI

A detailed breakdown of how long each phase of solar installation takes in Madison, based on local permit processing times and Madison Gas and Electric (MG&E) interconnection requirements.

3-5 weeks
Permit Timeline
$375
Permit Cost
6.8 kW
Recommended System
Madison Gas and Electric (MG&E)
Utility Provider

Interactive Timeline

Select your roof type below to see how it affects your installation timeline. Tile and slate roofs require additional mounting work.

Installation Timeline for Madison, WI

13 weeks
Estimated total time (~3 months)
1

Site Survey & Design

1 week

Engineer visits your home, designs system layout, and finalizes panel placement.

2

Permitting

3-5 weeks

Your installer submits building permits and HOA applications to your local jurisdiction.

3

Installation

1 day

Crew mounts racking, installs panels, wires inverter, and connects to your electrical panel.

4

Inspection

2 weeks

City building inspector verifies the installation meets code and safety requirements.

5

Utility Interconnection

5 weeks

Your utility installs a net meter and grants Permission to Operate (PTO).

Other Cities in Wisconsin

More Solar Resources for Madison

Ready to Go Solar in Madison, WI?

Ready to Go Solar in Madison?

We manage the entire process from permits to interconnection with Madison Gas and Electric (MG&E). Get a free quote and see your personalized timeline.