Solar Installation Timeline in New Orleans, LA

A detailed breakdown of how long each phase of solar installation takes in New Orleans, based on local permit processing times and Entergy New Orleans interconnection requirements.

3-5 weeks
Permit Timeline
$350
Permit Cost
7.6 kW
Recommended System
Entergy New Orleans
Utility Provider

Interactive Timeline

Select your roof type below to see how it affects your installation timeline. Tile and slate roofs require additional mounting work.

Installation Timeline for New Orleans, LA

13 weeks
Estimated total time (~3 months)
1

Site Survey & Design

1 week

Engineer visits your home, designs system layout, and finalizes panel placement.

2

Permitting

3-5 weeks

Your installer submits building permits and HOA applications to your local jurisdiction.

3

Installation

1 day

Crew mounts racking, installs panels, wires inverter, and connects to your electrical panel.

4

Inspection

2 weeks

City building inspector verifies the installation meets code and safety requirements.

5

Utility Interconnection

5 weeks

Your utility installs a net meter and grants Permission to Operate (PTO).

Other Cities in Louisiana

More Solar Resources for New Orleans

Ready to Go Solar in New Orleans, LA?

Ready to Go Solar in New Orleans?

We manage the entire process from permits to interconnection with Entergy New Orleans. Get a free quote and see your personalized timeline.

Get Your Free Quote