Solar Installation Timeline in Los Angeles, CA
A detailed breakdown of how long each phase of solar installation takes in Los Angeles, based on local permit processing times and Los Angeles Department of Water and Power (LADWP) interconnection requirements.
Interactive Timeline
Select your roof type below to see how it affects your installation timeline. Tile and slate roofs require additional mounting work.
Installation Timeline for Los Angeles, CA
Site Survey & Design
1 weekEngineer visits your home, designs system layout, and finalizes panel placement.
Permitting
4-8 weeksYour installer submits building permits and HOA applications to your local jurisdiction.
Installation
1 dayCrew mounts racking, installs panels, wires inverter, and connects to your electrical panel.
Inspection
2 weeksCity building inspector verifies the installation meets code and safety requirements.
Utility Interconnection
6 weeksYour utility installs a net meter and grants Permission to Operate (PTO).
Other Cities in California
More Solar Resources for Los Angeles
Ready to Go Solar in Los Angeles, CA?
Ready to Go Solar in Los Angeles?
We manage the entire process from permits to interconnection with Los Angeles Department of Water and Power (LADWP). Get a free quote and see your personalized timeline.
Get Your Free Quote