Solar Installation Timeline in Tempe, AZ

A detailed breakdown of how long each phase of solar installation takes in Tempe, based on local permit processing times and Salt River Project interconnection requirements.

2-3 weeks
Permit Timeline
$300
Permit Cost
6.0 kW
Recommended System
Salt River Project
Utility Provider

Interactive Timeline

Select your roof type below to see how it affects your installation timeline. Tile and slate roofs require additional mounting work.

Installation Timeline for Tempe, AZ

9 weeks
Estimated total time (~2.1 months)
1

Site Survey & Design

1 week

Engineer visits your home, designs system layout, and finalizes panel placement.

2

Permitting

2-3 weeks

Your installer submits building permits and HOA applications to your local jurisdiction.

3

Installation

1 day

Crew mounts racking, installs panels, wires inverter, and connects to your electrical panel.

4

Inspection

1 week

City building inspector verifies the installation meets code and safety requirements.

5

Utility Interconnection

3 weeks

Your utility installs a net meter and grants Permission to Operate (PTO).

Other Cities in Arizona

More Solar Resources for Tempe

Ready to Go Solar in Tempe, AZ?

Ready to Go Solar in Tempe?

We manage the entire process from permits to interconnection with Salt River Project. Get a free quote and see your personalized timeline.